This is where you will find the timeline of activity on the rebuild project

1/29/26 - Date of fire

1/30/26 - Accurate Reconstruction retained as construction expert by CAU

2/2/26 - Tom Licciardi of Accurate Reconstruction performed his inspection of the fire damaged homes.

2/5/26 - Tom's estimate submitted to CAU

2/9/26 - CAU approved our estimate

2/11/26 - Tom met with board via Zoom

2/12/26 - Accurate was notified that we were awarded the rebuild contract

2/24/26 - Architect inspected

2/24/26 - All homeowners received a full listing of all repairs scheduled for each of their homes

3/12/26 - The architect is finishing up his plans. He has committed to having them to us by Wednesday, 3/18. Once received, we will be able to submit our permit application package to the town. In the meantime, please have your individual homeowner's insurance adjusters reach out to us directly to discuss your individual claims.

Copyright © 2026 Accurate Reconstruction at Regency Pointe - All Rights Reserved.


Powered by

This website uses cookies.

We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.

Accept